The project was liquidated with penalties removed without support. In addition, it has not been transferred, a fact that prevents its delivery to the beneficiary population and maintenance. In the work to improve the irrigation water system of the Pacora users commission in Lambayeque, in charge of the Regional Management of Agriculture, an external consultant was hired to calculate the technical and financial settlement who contemplated penalties for S/ 144,085, while the auditors of the General Comptrollers Office detected that said concept amounts to S/ 197,500.
In report No. 030-2024-OCI/0989-SCC it is indicated that the consultant eliminated penalties for non-attendance of key personnel without attaching the supporting documentation, despite being obliged to issue detailed calculations.
In addition, it was identified that more than 48 business days passed since the technical report was submitted to issue the settlement resolution; however, this has not been published. This fact postpones the transfer of the work to the Pacora Users Board and, therefore, the lack of maintenance is not provided, postponing the delivery of the project to the beneficiary population.
In this regard, the control commission identified that due to the lack of this maintenance, there is the presence of water and stones of different sizes in the canal that would cause overload at the time of entering into operation, which could generate cracks in its structure and affect the durability of the work that has a cost greater than S/ 18 million.
Likewise, it warns of the lack of sealing between the expansion and contraction joints of the canal and deficiencies in the seal already placed in other sections. These situations were observed by the supervision in December 2023, but until the issuance of the report they were not corrected.
Crags and exposure of the reinforcing steel of the vehicular bridge were also evident. This demonstrates an inadequate coating and that the specifications of the technical file were not followed, which puts the quality and useful life of the project at risk.
Since the beginning of the work, ten control milestones were communicated to the head of the entity in order for him to adopt preventive actions to ensure the public purpose and the achievement of the objectives of the work. The report is published in the Control Services Report Search Engine.