📋 Tender Overview
The General Comptrollers Office detected deficiencies in the execution of the road service improvement project in the Villa del Lago and Chanu Chanu I and III stage urbanizations of the city of Puno. This work, with a budget of S/ 5,210,447, presents risks to the safety of workers and the population in general.
In the Concurrent Control Report No. 019-2024-OCI/0463-SCC it was found that the contractor and the supervisor of the work had failed to comply with basic safety and quality standards. Among the main irregularities identified are:
Assignment of personnel from the supervisory staff who are unaware of their participation during the execution of the work, as well as the link with the contractor, which affects the technical direction of the work according to the specialty.
Simultaneous participation of key personnel of the executing contractor as an official in another entity, a situation that harms the technical direction of the work.
Both the contractor and the supervisor have key personnel who do not meet the requirements established by the corresponding professional associations.
The lack of adequate signage in the construction area exposes road users and neighbors to danger.
A large number of workers lack the necessary personal protective equipment. For example, workers were observed working without helmets, gloves or reflective vests, which exposes them to the risk of work accidents.
These irregularities could lead to breach of contract and the application of penalties to those responsible. The Comptroller General recommended taking the necessary corrective measures to guarantee the safety of workers and the quality of the work.