📋 Tender Overview
The Comptroller Generals Office warned of situations that may affect the quality of the project Improving the trafficability of the Otuzco - Combayo highway, a situation that could affect 3,620 beneficiaries. This project is valued at S/ 66,842,641, under the responsibility of the district municipality of La Encanada.
According to the Control Milestone Report No. 029-2024-OCI/1512-SCC, during the visit to the site in August 2024, the presence of workers carrying out construction work on a gabion wall (stone structure and steel mesh) was noted without technical supervision or the presence of the inspector or supervisor who can validate the work, in addition to the fact that said work had been suspended since July 17, 2024.
In addition, the commission warned that the formwork removal of the pontoon called Sangal (drainage structure) is being carried out, work that should not have been carried out during a suspension period without technical supervision since it can cause damage to the structure and become a potential danger for people who are working.
The existence of a drainage manhole located in the center of the road that does not have the corresponding cover or safety signs was also reported, which generates a high risk of accidents for pedestrians and vehicles that travel through the area.
Likewise, a second drainage manhole was found on the road that has been left with a level higher than that of the platform, which constitutes a high risk of accidents for pedestrians and vehicles.
Other situations reported are the delay in the payment procedures for appraisals of the physical execution of the balance of the work, which could generate interest in favor of the contractor due to late payment of the aforementioned appraisals and affect the resources of the entity.
The control report was notified to the head of the District Municipality of La Encanada in order to adopt the corresponding preventive and corrective actions. The report is published in the Control Services Report Search Engine.