📋 Tender Overview
The Office of the Comptroller General showed that officials and servants of the District Municipality of Tintay from previous administrations allowed resources destined for the construction of Basic Sanitation Units (UBS) of the basic sanitation work of Tintay to be used for a purpose other than the project.
This situation contravenes the provisions of the technical file of the work and the regulations in force, which caused damage to 277 beneficiaries who do not have full access to this service.
The work to improve and expand drinking water and basic sanitation services in the communities of Visacocha, Chihuapampa, Pampatama, Minune, San Mateo, Huancarpuquio and Taquebamba in the district of Tintay, province of Aymaraes, was executed with a budget of S/ 17,356,748 with the aim of reducing endemic diseases in the aforementioned localities to address the health gap and improve the living conditions of the population.
In the Specific Control Service Report No. 006-2023-2-0348-SCE, which corresponds to May 21, 2015 to June 18, 2019, it is specified that the legal advisor, the head of the Investment Executing Unit and the work coordinator of the entity issued favorable reports through which they approved the modifications to the technical file of the work (additional n°1 and n°2) without considering the technical justification in accordance with applicable regulations.
The entity's servants approved and allowed the modification of the dimensioning (size or production capacity of the project) of the work by eliminating 267 residential UBS and 10 institutional UBS projected in the technical file of the work, allocating its budget of S/ 2,304,080 for the construction of the sewerage system with treatment plant, without meeting the objectives of the investment project and outside the regulations.
It was also evidenced that during the technical-financial settlement stage of the work, the entity signed a conciliation agreement that favored the contractor by allowing him to partially correct the observations made by the specialist hired to evaluate the state of the work. However, the supervisory committee found that these observations persist today, among others.
As a result of the control report, seven officials and public servants with alleged criminal responsibility were identified, which was sent to the Public Prosecutor's Office Specialized in Corruption Crimes for the initiation of criminal proceedings against those involved in the acts of the irregularity. The report is published in the Control Services Report Finder.