📋 Tender Overview
The Office of the Comptroller General detected irregularities in the work to improve and expand the sewerage system in the town of Lamas, such as the absence of key personnel for supervision and/or execution, failure to deliver the deadline for the review of the technical file and avoid possible deficiencies, among other adverse situations. The work is being carried out by the Provincial Municipality of Lamas with an investment of more than S/ 37 million.
In Control Milestone Report No. 4246-2024-CG/GRSM-SCC, it was determined that the entity approved valuation No. 1 for the month of January 2024, in which the supervision did not carry out the corresponding calculation of penalties for the absence of key personnel without justification, despite the fact that it warned through the workbook, a situation that would generate an adverse consequence of S/ 424,773.57 due to the non-application of penalties.
Likewise, the execution began with a work consultant hired by a service order by the supervisory entity, Emapa San Martin S.A., without the selection procedure to hire the supervisor being convened, in addition to not having the minimum technical staff required for the supervision of the work, which violates the state contracting regulations and generates the risk of the legitimacy of the supervision and approval of the work. valuations that would become illegal.
The control commission identified that the contractor did not comply with delivering the review of the technical file within the period stipulated in the regulations of the State Procurement Law, a situation that generates the risk of not timely warning of possible deficiencies in the technical file.
On the other hand, the contractor does not comply with the preparation and implementation of the social intervention work plan, a situation that
would generate an adverse consequence on March 2 for the entity of S/. 783,874.49 if the penalties for breach of contract are not applied.
An additional point is that the contractor does not comply with the approval process of the archaeological monitoring plan before the Ministry of Culture, a situation that would generate suspension of the execution deadline, in addition to an adverse consequence in March 2024 for the entity of S/. 783,874.49 by not applying penalties for breach of contract.
The report has been notified to the Provincial Municipality of Lamas so that it can take the appropriate corrective measures. In addition, it is published on the website www.gob.pe/contraloria, in accordance with the Law on the Strengthening of the Comptroller's Office and the National Control System.