📋 Tender Overview
This week the asphalt mix paving tasks began in the Itacurub bypass as part of the expansion and duplication of route PY02 in charge of Rutas del EsteThe work will help expedite vehicular traffic in the department of Cordillera through the beltway in said city.The new road will be 7 kilometers long and runs from km 85.5 access roundabout to Valenzuela of Itacurub to km 92.3 east link.The project contemplates the following characteristics 2 separate carriageways with 2 medians and a New Jersey-type concrete barrier with 2 3.5-meter lanes and 2.5-meter shoulders.If all goes well it is estimated that in June of this year the variant may already be operational to benefit all users.