📋 Tender Overview
Operators from the TC Pilar Consortium continue loading slab on the 626-meter bridge located over the Paso P stream in the department of eembuc.The bridge is part of the asphalt paving work on the Alberdi detour section and the Tebicuary river lot 1.If all goes according to schedule the bridge should be ready by the end of this month. Added to this are the jobs in the urban area of Villa Franca and lime soil. The work in general has an advance of 85 and is a source of employment for 400 people. It covers 51.56 kilometers which also includes the improvement of the urban crossing of Villa Franca which adds some 2.05 km more to the work. The project included a second section that goes from the Tebicuary River to the departmental capital a sector that is already fully completed and enabled for vehicular traffic.