📋 Tender Overview
This morning the laying of the asphalt concrete base began in the connection section between the route to Puerto Falcn and the access viaduct to the Hroes del Chaco Bridge Chacoi side. The tasks correspond to the road section of the bridge which includes accesses and viaducts totaling more than 7 km of roads from the Costanera Norte to the Remanso - Falcn route in the Western Region.In general the construction of this emblematic footbridge registers an advance of 85 as stated in the last certificate of works.It should be remembered that this weekend the concreting of the tenth segment of support 55 was completed while in support 54 the segment 12 was concreted in the Costanera Norte sector. With this we reached 60 meters of the 150 that separates the access viaduct from the bridge.As work is being done on the bridge structure completion tasks and complementary works are also being carried out such as the construction of a ridge a gutter ridge a sidewalk a bicycle lane installation of flex beams and slope protection.