📋 Tender Overview
The construction work of the Paso Pé bridge, located in the first section of the Alberdi – Pilar detour route, is nearing completion with a general progress of around 97%, according to the contractor's report.
This bridge is part of the asphalt paving works for Lot 1 that connects the Alberdi Diversion with the Tebicuary River, in the department of Ñeembucú.
Regarding the construction of the route, the tasks mark a general progress of 108.3% executed out of a total of 120%, according to the amending agreement and the last update of the schedule.
Up to now, there are 34 km of asphalt, and work has also started on the urban crossing of Villa Franca, 2.05 km long, thus totaling 53 km of new asphalt to be built. All this, in charge of the TC Pilar Consortium.
The Pilar-Alberdi detour route is part of a strategic 90-kilometer road corridor that will directly benefit the inhabitants of the municipalities of Villa Franca, Mburicá, San Juan Bautista de Ñeembucú, Tacuara and Pilar, since it will save them significant travel time from and to the country's capital, in turn promoting the social and economic development of the entire tenth department.