Despite construction work, the OBB offer reliable mobility offer and extensive replacement traffic.
Working enables functioning infrastructure and safe train operation
Even during the locks, rail vehicles can be on the railway line.
(Linz, June 30, 2025) - A lot is happening in summer: Mattigtalbahn, Innkreisbahn, Danube bank, Pyhrn route, Almtalbahn, Muhlkreisbahn and the Salzkammergutstres - maintenance work and construction activities take place. So that passengers continue to come from A to B, a rail replacement traffic is set up in the respective sections of the route. The maintenance measures along all routes enable a functioning infrastructure and thus a safe train operation for travelers. In order to avoid building activities over a longer period of time, measures are bundled along the routes and entire sections of the route are served. Despite construction work, the OBB offer reliable mobility offer and extensive replacement traffic.
Locking of railway crossings
During the locks, there are also work on railway crossings (EK) to increase security. Therefore, some of these are blocked for road traffic. Despite the locks, rail vehicles can be on the railway line. It is therefore particularly important to observe the signs and path lines to railway crossings.
Mattigtalbahn
Rail replacement traffic Neumarkt am Wallersee - Braunau from July 18 to August 31, 2025
The modernization of the Mattigtalbahn continues to pick up speed in the Friedburg - Braunau section. In order to increase security on the route and as an important prerequisite for electrification, 7 railway crossings will be rebuilt or technically secured this year and 13 railway crossings are left. The Teichstatt stop is also modernized and, among other things, receives barrier-free access, a waiting koje, infomonitors, a ticket machine and a contemporary bike & ride system. In order to optimally use the summer lock, the state of Upper Austria is building a cross -country bridge in Mattighofen during this period for the Mattighofen bypass. In addition, ramming and masting work for over -line construction takes place in the Friedburg - Braunau section. The lock is also used to renew drainage systems to protect against flooding.
Innkreisbahn
Rail replacement traffic Ried im Innkreis - Simbach/Inn from 7 to 18 August 2025
During the barrier period, two existing railway crossings are abandoned in the municipality of St. Peter am Hart and replaced by a new, modern solution. At the same time, the L1100 Hagenaustrasse takes place and the construction of an accompanying walking and cycle path. These measures are the prerequisite for the integration of the Mattigtalbahn into the Salzburg operating tour center.
Bank bank
Rail replacement in two stages:
Mauthausen-St. Nikola strudes from July 7 to August 10, 2025
Grein-Bad Kreuzen-St. Nikola-Struden from August 10 to September 5, 2025
Along the Donauuferbahn, work for the underground renovation and renewal of tracks and soft take place during the lock, for example in the Aisthofen section-Perg or in the Dornach-Grein-Bad area. In addition, the completion or expansion of three electronic signal boxes (ESTW) is being used. These enable reliable, automatic control of rail operations. The new ESTW in Grein-Bad Kreuzen and St. Nikola-Struden as well as the expansion of the ESTW in Arbing are further steps in order to be able to control the course and signals along the Danube bank railway safely and reliably in the future.
Pyhrn
Rail replacement in several stages:
1. to August 28, 2025 between Rohr-Bad-Bad Hall and Klaus or for S-Bahne between Wartberg and Micheldorf
August 28 to September 8, 2025 between Nettingsdorf and Klaus or for S-Bahnen between Nettingsdorf and Micheldorf
Additionally rail replacement traffic for individual trains at night.
In connection with the progressive modernization of the Micheldorf train station, barriers on the Pyhrn route are necessary this summer. In the interests of traffic safety, another three railway crossings will also be abandoned around Micheldorf train station at the beginning of August 2025 (train station, Heiligenkreuzer Strasse and Bader-Moser-Strasse). These are replaced by new, safer underconses. In order to advance the work quickly, roads are blocked in sections and traffic is redirected. By the beginning of September 2025, the new crossings will be gradually opened for traffic. Furthermore, there are extensive track and sowing new systems along the route along the route.
Almtalbahn
Rail replacement traffic Wels Hbf. - Grunau in the Almtal from July 7 to September 5, 2025
The lock along the Almtalbahn is used for service and repair work that ensure safe train operation. For example, track construction work in the section between Pettenbach and Steinbachbrucke as well as work on bridges at Wels Mass and between Oberhart and Unterhart. Also on EisenbaCrossings along the route take place and measures to increase security.
Muhlkreisbahn
Rail replacement Linz Urfahr-Aigen-Schlagl from July 7 to 27, 2025
Service and repair measures take place along the Muhlkreisbahn to ensure safe train operation. Tracking takes place in Rottenegg and Puchenau West, and there are also work on various railway crossings. The security systems, tracks and lanes are adapted to several railway crossings. Work on the roadway also takes place at the EK at the Iglmuhle stop. Therefore, the Iglmuhl district road must be blocked in the period from Monday, July 21 to Friday, July 25th.
Salt chamber
Rail traffic on rail and long-distance traffic:
Attnang-Puchheim-Stainach-Endning from July 5 to August 11, 2025
Gmunden - Bad Ischl from July 5 to August 11, 2025
This year the focus of the work in the municipality of Ebensee is with track and earth construction work in Langwies as well as the renewal of overhead line, tracks and switches in Ebensee station. Due to the track construction work, there is temporarily locking railway crossings in Ebensee. As of next year, work in E