📋 Tender Overview
Maintenance work on tracks, bridges and passages lead to rail replacement traffic
Construction work at Raaba station runs according to schedule
Rail replacement between Graz and Gleisdorf from July 05 to September 7, 2025
(Graz, June 20, 2025) In order for travelers and goods to be on the way on the climate -friendly rail on the way, railway lines need regular service. The OBB will carry out renewal and maintenance work on the Styrian Ostbahn in the next few weeks. The extensive work is bundled and include track work, the renewal of through gaps and bridge work. Due to the construction work, a rail replacement traffic between Graz and Gleisdorf is set up by bus.
In addition, the major project Modernization Bahnhof Raaba continues, the work is on schedule.
Rail replacement between Graz and Gleisdorf
Due to the construction work mentioned, the route must be blocked in sections in summer, buses are used for rail replacement. We request travelers to find out about the planned travel route before starting travel, as there can be deviations from the timetable.
From 05 July to September 7, 2025
Modernization Raaba station runs according to the plan
Since 2024, work has been done intensively on the expansion of the S-Bahn stop Raaba. By December 2026, a new local transport node will be built, which will include both a modern, barrier -free train station and bus stops. Currently, work is being carried out intensively on the state road underpass with accompanying walking and bike path. The walking and cycle path underpass on Tiefentalweg will be completed at the end of June. Further construction phases are still in implementation.
The railway crossings (EK) on the flower path and savings path as well as the provisional EK of the state road L370 will be removed permanently in the coming weeks and removed from July 5.
The overall completion of the project is planned in December 2026.
Customer information
We try to keep the inconveniences as low as possible due to the construction work, but increased noise and dust development can occur. The OBB ask for understanding and request travelers to find out about the planned travel route before starting travel. Current information on www.oebb.at, at the OBB-Kund: Interior service 05-1717, in the Scotty app or on the social media channels. Information about the construction work can also be called up on the homepage www.infrastructure.oebb.at.