📋 Tender Overview

In Maria Anzbach, work at the new train station is in full swing. From September 9, 2025, the trains are already departing from the new platform.
The daily paths change significantly from Tuesday, September 9, 2025 for train commuters in Maria Zubbach. The trains in both directions then no longer stop at the old train station, but already on the new platform 2. From this point on, access takes place via the new opening road from the roundabout. The new Park & Ride system goes into operation with a reduced number of parking space.
In the neighboring Neulengbach city, the trains also run from platform 2. Between the Neulengbach City stop and the Neulengbach train station, the construction work focuses primarily on overhead work.
Park & ride system as well as passing through the person blocked
In Maria Anzbach, the old Park & Ride facility with the access via the Kronesstrasse for the further renovation work is closed. In the upcoming construction phase until December 2025 there is no direct access to the new train station from there. The old passage passage must also be blocked again. From September 9 to November 7, 2025, the use of this crossing is not possible. The detour for pedestrians: inside runs on the Kronesstrasse and Schwabstrasse and via the connecting path to Mozartgasse.
New footpath at the beginning of the next construction phase
In order to get to the new train station more easily on foot, the new footpath above the cemetery will be equipped with a provisional connecting staircase to the new platform 2.
The upcoming construction phase lasts around mid -December 2025. During this period, the new platform 1 including platform roof and equipment will be built. The personal passage is completed, the existing platform 1 is removed. In the meantime, the use of the railway walkway in this area is not possible. As an alternative route for pedestrians: a footpath is adapted to the Kronesstrasse inside. Cyclists: Outside the bike path along the B44.
Since the lifts for the new platforms can only be installed at the end of the construction work and a subsequent acceptance from the TUV is required, the new train station is temporarily not yet accessible.
Further work in the municipal area
Since the southern track track has to be blocked for the work at the new train station from September, the construction phase can also be used for further work along the route. So there will be works on the drainage systems between Hutten and Hofstatt. In addition, new cable troughs will be moved between Maria Anzbach and Hofstatt or further to Neulengbach. For this purpose, two places are temporarily built to the single-track of two-way vehicles, one in under Oberndorf west of Huttenstrasse and one along the Kronesstrasse in the area between Kokoschka and Wienerwaldgasse. A total of five temporary areas are also set up along the railway area in the entire municipal area, where building materials can be stored during the work. In these areas, due to loading activities, waiting times of up to 15 minutes can occur.
Operation work in Neulengbach
Until mid -December, work on the overhead lines will take place between the Neulengbach Stadt stop and the Neulengbach train station. This work is carried out both during the day and at night. From September 9th, all trains in Neulengbach City on platform 2. Furthermore, the structure of the Laabenbachviaduct will be reinforced and damnation is carried out between Neulengbach and Eichgraben-Altlengbach.
Changes from Tuesday, September 9, 2025, in Maria Anzbach:
Sliding platform 1, all trains drive off the new train station, platform 2. Attention: The lift is not yet in operation, so the platform is therefore not accessible.
Parking on the new Park & Ride system, lock of the old Park & Ride system.
Sliding Personal transition at the old train station until November 7, 2025 - detour via Kronesstrasse, Schwabstrasse and Mozartgasse. New footpath above the cemetery.
Slant in the area of the construction site-provisional footpath, bike redirection via cycle path B44
Further work in the entire municipal area along the train.
Night work in detail:
August 30 - December 14, 2025: In this construction phase, we always work in different places at night, especially:
September 8 - September 12, 2025 and September 29 to October 10, 2025: Working in the area of the new Maria Anzbach train station, especially on the overhead line and in the area of the new personal passage
September 15-October 3, 2025: Ramming and setting up the overhead line masts on the west head of the Neulengbach train station, work for the new overhead line aggregate
October 6 - October 17, 2025: Pre -mounting of the overhead lines in Neulengbach station
November 24 to November 29, 2025: track construction work between the former Unter-Oberndorf and Hofstatt stops
November 30 - December 14, 2025: Assembly of the overhead lines on the viaduct
In addition to the existing timetable changes, train failures and rail replacement reversalsThe trains of the lines Rex51 and S50 drive in sections on the rail replacement traffic on Thursday, September 11, 2025 between 00:00 and 01:25.

🔍 Key Information

📄
Tender Reference No.
522170697
📅
Publication Date
29 Aug 2025
🌐
Sector
Railways
📝
Notice Type
News
📍
Location
Austria

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 29 Aug 2025
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Austria
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…