📋 Tender Overview
The construction of the new infrastructure of the Jose Carlos Mariategui educational institution registers an accumulated physical progress of 30% in the province of Islay. The project is carried out on a total area of 10,033.69 m2 and will benefit more than 550 students in the area.
The work is carried out under the Works for Taxes modality, a mechanism that allows the development of public investment in educational infrastructure for the benefit of the community.
The contingency infrastructure is enabled for the current school year, allowing students to develop their academic activities while the execution of the main project continues.
The construction resident, Architect Marlon Davila, reported that the team executes structures in modules intended for primary and secondary school. He indicated that the structural work has already been completed in modules C, D, E, F and G, while work continues in modules A and H, and the start of intervention is expected in module B. Subsequently, the project will continue with pending foundation work, the installation of metal coverings in the primary and secondary playgrounds and the execution of architectural and equipment items.
The work has personnel distributed in eight work fronts. As the execution of the items progresses, the number of workers in the field will progressively increase until reaching approximately 140 workers.
The new infrastructure will have modules for primary and secondary school, teaching classrooms, independent stairs, administrative and well-being environments, dressing rooms, elevated tank and cistern, tanks, perimeter fence, access ramp for people with disabilities, pedestrian bridge, stands, slabs, sidewalks, retaining walls and metal covers in patios, which will allow the development of educational activities of the student community.