A lot of hard work was done in and around Zwolle from Monday 29 April to Thursday 2 May. Train traffic resumed this morning. With photos we look back on the work that has been done in Zwolle.
Worked in eleven locations
"A shutdown of Zwolle is unique," says Aniek Montoya-Poelhekke, construction manager at ProRail. "That's why work was carried out at no fewer than eleven locations in and around Zwolle at the same time. The twelve wooden bridge sections of the Passerelle are in place, the platform roofs are clean, viaducts have been painted and NABO have been tackled. Everything went according to plan, I'm proud of that."
The contours of the Passerelle are already clearly visible. On Monday afternoon, the hoisting of the wooden bridge sections started. This was done with two large cranes, which were working at the same time. The largest bridge section, which is 43 metres long and weighs 60 tonnes, was the first to be tackled. The hoisting of one beam took about seven hours. At the end of the day on Wednesday, it was the turn of the last girder.