📋 Tender Overview
Mid-August is the moment for the Oosterhoutseweg N631 underpass project in Rijen. Then the tunnel box is retracted under the track. Contractor Heijmans will do this between Monday 14 and Friday 18 August. There will be no trains for five days and buses will be used.
The decommissioning of the railway does not only apply to Breda-Tilburg; also between Tilburg-Den Bosch and Tilburg-Boxtel there are no trains running on those days. By combining many different track activities, we make optimal use of the time we have to work on the track.
N631 as a construction site
On 10 August, Heijmans will start preparatory work: the N631 will be set up as a construction site so that materials can be stored there during the work. The N631 is therefore closed to traffic during the railway works.
After the track was taken out of service on 14 August, we dug a construction pit. This is how we make room for the tunnel. After the groundwork, we slide the tunnel box into place in 26 hours. Then we rebuild the track. After August 18, the trains can run again. The N631 will reopen to traffic from Monday morning 21 August at 5.00 am.
Special construction
The construction of this underpass is special, because in this week all pre-conceived phases, techniques, processes and disciplines come together. During decommissioning, this all falls into place.
The execution of the concrete work is also not standard, but really a piece of craftsmanship. The walls of 7.5 meters slope backwards and have a special ribbed structure.
In addition, this tunnel is particularly large. Heijmans does not slide a 4800-tonne tunnel weighing 45 by 25 by 7.50 metres into place every day. During the decommissioning, a team of fifty people is working on location at the same time.