📋 Tender Overview
In Heerhugowaard, ProRail is about to carry out spectacular work on the future Zuidtangent railway underpass. From 18 to 23 March, we will be working 24 hours a day to put the track deck in place. The track deck is the concrete structure that the trains will run over. No trains will be running during this period. Marcel Martens, construction manager: "It will be a bit of a struggle, especially at night."
Planning fits like a puzzle
“We’re going to do a lot of work in the six days,” says Frank Derlagen, chief contractor at Mobilis-Hegeman. “First, we’ll remove the tracks and dig out the railway embankment. Then we’ll drive support piles where the track used to be and also build sheet piles there. On Friday, we’ll drive the track deck into place, a spectacular job.” Marcel Martens, the construction manager from ProRail, confirms this: “We’re putting almost 2 million kilos of concrete on wheels, to put it simply, and we’re driving it into the hole in the railway embankment with centimetre precision. That’s just cool. Real craftsmanship.”
The tight schedule does cause night-time disruption for the surrounding area: “To fit everything into six days, we have to do some piling at night, for example. That’s really annoying for the surrounding area, but it wouldn’t fit otherwise. And we want to stop the train traffic for as short a time as possible.” Frank adds: “It was really a matter of trial and error, everything now fits together like a puzzle. We hope for understanding from the surrounding area, after this the disruptive work will be over.” Once the track deck is in place, the track will be rebuilt and the track safety will be adjusted. Frank: “The trains will then be able to run again. And we will continue with the rest of the project.”