An important milestone has been reached in the construction of the new underpass in Rijen. Today, Tuesday 15 August, the particularly large tunnel will be moved in. With precision and careful planning, the tunnel construction is gradually pushed to the designated location. This exciting job is completed in just over 26 hours.
Special technique
Sliding in the tunnel is a special technique that has rarely been used in the Netherlands. Our colleagues from Heijmans Infra Civil Specialisms carry out this. By means of up to ten push cylinders including stamp constructions, the tunnel is pushed to its final location. The special thing about this operation is that the underpass slides over the sand instead of over the sliding track.
During the work there were several exciting moments. For example, prior to the decommissioning of the railway, the groundwater level had to be lowered. Fortunately, that succeeded and yesterday, Monday 14 August, we started moving the underpass to the final position. At the end of the decommissioning, we look forward to the moment when the very first train runs over the new underpass. This is expected in the early morning of Friday 19 August to Saturday 20 August.
Safer traffic
The new underpass will not only ease the flow of traffic, but also increase the safety of road users. Traffic is expected to be able to drive through the new tunnel from the summer of 2024.
The work is part of the N631 Rijen-Oosterhout project of the province of North Brabant. For safety reasons, it is not possible to visit the construction site or watch live. We make a timelapse of the work.