📋 Tender Overview
Above the new British passage at Amsterdam Zuid station we are building a new train platform for tracks 1 and 2. For that reason the platform was closed and there were fewer trains to and from Amsterdam Zuid until 27 March. Planning completed construction went according to planning. Earlier Building Combination Nieuw-Zuid (Mobilis Boskalis and Van Gelder) worked in the British passage on the walls on which the new platform will rest. In the meantime the builders are busy with the platform itself above the ground. The new train platform will be accessible again from 27 March. Trains then run to and from Amsterdam Zuid station again according to the normal timetable. The construction of the new platform started with a completely new steel construction.
On top of that prefab concrete plates have been placed. On top of that we braid a low reinforcement on which we deposit concrete. The platform must soon be strong enough to be able to carry the weight of the new platform caps in addition to a large number of travelers. Once the concrete has hardened Building combination New South can start with the finish of the platform including applying a glass ceiling of the British passage. This glass will soon provide daylight in the new passage. Placing the platform caps for both platforms will follow later in 2025. Two train platforms we went through the same order in January at the Perron for Spoor 3 and 4. We also replaced this temporary train platform above the British passage for a definitive platform. Moreover between 12 to 26 March one train track could be taken at the station station. This was necessary for major maintenance that was carried out at the connection to Schiphol.
We have gratefully made use of the extra time we had to build the new train platform. Renovation Station Amsterdam Zuidstation Amsterdam Zuid bursts out of its seams. To be able to process the growing number of travelers we are building an extra access: the British passage. As soon as it is open at the latest in 2027 we start the Minerva Passage. Read more Read Meermeer about: Work Amsterdam South Renovation Station Station of Noord-Holland can again by train24 March 2025next Construction phase at Amsterdam Central of start 20 March 2025 work at Perron 3-4 Station Nijmegen 11 March 2025 Are you satisfied with the information on this page? Yes No What can we do to improve the information? Send feedback thank you SpoorwerkCwoon or do you work within 300 meters from the track? Then use our railway work. You can immediately see which work is planned in your neighborhood.