Engineering Oil and Gas

Netherlands Mammoet Successfully Tender

πŸ“„ Tender ID: 448700204 πŸ“… Published: 09 Nov 2019

πŸ“‹ Tender Overview

Mammoet contributed to the Visakh Refinery Modernisation Project by safely and successfully completing lifting of 5 major components at 3 lifting positions at the refinery on time. Owned by a state-owned company Hindustan Petroleum Corporation Limited HPCL the project entails modernisation and enhancement of its refining capacity from 8.33MMTPA to 15MMTPA at a new process area on the east of its original plant. LT Hydrocarbon Engineering the biggest EPC contractor in India as well as Mammoets long-time loyal customer has undertaken the EPC engineering procurement and construction task and engaged Mammoets MSG80 Ring Crane our module sliding gantry with 3000 Ton lifting capacity.What makes this project unique is that the close coordination and carefully engineered lifting operation among HPCL LT and Mammoet made possible to overcome logistical and operational challenges without compromising safety and schedule. Mammoet lifted 5 major components at 3 different lifting positions 2 columns at Crude Distillation Unit CDU and Vacuum Distillation Unit VDU followed by 3 reactors and other lighter columns at Full-Conversion Hydro-Cracker Unit FCHCU. Stage 1 Reactor at FCHCU area weighs 1646Ton being the heaviest reactor ever installed in India. Relocation of a 3000 Ton class crane is already a big operation by itself. With support from LT Mammoet took the modularised transport approach by moving the crane in big blocks to expedite the two relocation activities.Another ingenious solution is a 2000Te capacity tailing frame mounted on SPMT Self-propelled module transporter. For lifting of the Stage 1 Reactor none of the cranes on site had a sufficient lifting capacity to function as a tailing crane for MSG80. Bringing in a heavy-duty crane just for one lift was not an economical solution on top of the fact that the site was a highly congested area with no practical space to place such a large tailing crane. Mammoet provided good mix of the solution with a main crane strong enough to lift all the heavy items for the project and the in-house designed tailing frame on SPMT that eliminated the need of a heavy-duty tailing crane and saved its space. This significantly improved our overall cost efficiency and productivity of the surrounding construction activity says Mr V. Muthuraman Deputy General Manager of Plant and Machinery LT Hydrocarbon Engineering.

πŸ” Key Information

πŸ“„
Tender Reference No.
448700204
πŸ“…
Publication Date
09 Nov 2019
🌐
Sector
Engineering
πŸ“
Notice Type
News
πŸ“
Location
Netherlands

πŸ“ Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
πŸ•’ Submission deadline
0
days remaining Β· 09 Nov 2019
πŸ”” Set Alert

🧭 Quick Facts

Authority N/A
Country Netherlands
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…