It's over: with the insertion of two ludicrous roof sections for the new passenger tunnel of Amsterdam Zuid station, the Brittenpassage, the eight-day work of the Zuidasdok project has been completely successful.
Wet conditions
Of the seven huge roof sections for the additional passenger tunnel, five are now in place. The work started in wet conditions, with the asphalt of the A10 being removed layer by layer and the dike on which the A10 is located was excavated over 100 meters. We built on the work that was carried out last year, now with sometimes up to 200 colleagues a day. For example, we placed the slides for the sliding operation of the roof parts on the foundation pipes that we put into the ground last year and we removed the last remnant of the old Amstelveen arch. For example, we carefully worked towards retracting the roof parts.
The weather wasn't good
Retracting roof sections
On Wednesday, August 9, the time had come and we moved the roof parts to their place at a speed of about eight meters per hour. Four hydraulic jacks pushed the two giant sections of about 33 meters north to their place under the train tracks and the A10. On Thursday 10 August, the most important job during the eight-day closure of the A10 South was successfully completed.
Station Amsterdam Zuid verwerkt nu al ruim 80.000 reizigers per dag. Met de komst van de Noord/Zuidlijn in 2018 en de groei van het treinverkeer op het traject Schiphol-Amsterdam-Almere-Lelystad worden dat er zeker drie keer zoveel: 250.000 reizigers per dag in 2030. Om daarvoor ruimte te maken brachten we ook een flauwe bocht in de A10 aan.
Excavation of the Brittenpassage
With five of the seven roof sections in place, it is not yet finished and we will continue to excavate the Brittenpassage under the roof parts. The last roof parts will be retracted at a later date. The Britten passage must be completed by 2027.