Over the past 16 days, Den Helder Zuid station has been almost completely demolished and then rebuilt. Trains have been running again since the morning of 24 March. “Everything has been renewed or given a facelift,” says John Nieuwstad, construction manager of ProRail.
Travelers welcomed
Train passengers were welcomed back to the train this morning with a local cake. It marks the end of 16 days of bus transport in the Kop van Noord-Holland. “That really caused some inconvenience, but it was for a good cause. People reacted very positively. The station shines like never before.” The complete renovation of the station was about time, John explains. “Passengers rated the station quite poorly. We hope that we have now turned that around.”
All over again
To achieve this turnaround, we carried out major work over the past 16 days. John: “We started by completely demolishing the platforms. Then we renewed the foundations and rebuilt the platforms. The platforms were then fitted with new furniture and the number of waiting rooms was expanded. This makes waiting for your train more pleasant.” Not unimportant in the empty environment in which the station is (still) located: “It is almost always windy here,” adds John, who lives in Den Helder himself. The stairs were also adapted to make them more accessible. And the station tunnel, equipped with a work of art, was renovated.
Almost done
The biggest works are behind us, but we are not quite finished yet. John and his team will be putting the finishing touches on the project until May. “We are still installing a large waiting room so that passengers can wait for the train in the dry, and there is still some finishing to be done. But the most important thing is that the trains are running again!”