The railway bridge near Alkmaar station is expected to be repaired by the end of next week. Since 11 May, the bridge can only be opened once a day, because the bridge cannot be operated remotely due to a cable break.
Cables hit
During work by a third party, three underground cables were hit. These are crucial cables that enable remote operation of the railway bridge. Due to the cable break, the bridge cannot be operated remotely, but a bridge keeper must come to the bridge to do this. This bridge keeper must also have specific expertise. There are not enough bridge keepers with this expertise available to open the bridge more often.
Recovery already started
As a result, shipping has suffered a lot from the limited opening in recent weeks, so we have been looking hard for a solution. It's here now.
Yesterday, Thursday 1 June, the restoration of the operation of the bridge started. The recovery is expected to last until the end of next week. In the period of recovery, the bridge can be opened manually. We do this, just like now, once a day. After the recovery, it is again possible to operate the bridge remotely and this can be done more often.