Comptroller warns that actions are missing to resume electric power project in Campus IIAncash. - The Comptroller General warned that the National University of Santa (UNS) has not executed concrete actions for the restart of the electric power work of Campus II, despite the fact that the causes that originated its suspension in December of 2022 have already been served, a fact that generates delays in the culmination of the project and affects the student population of several faculties.

As detailed by the Control Milestone Report No. 6538-2025-CG/GRAN-SCC, since May 27, 2025, the causes of the third suspension of the work would have been exceeded, which were the lack of approval of the Environmental Adaptation and Management Program-Pama by the General Directorate of Educational Infrastructure of the Ministry of Education (MINEDU) and the update of the technical conformity of the technical conformity of Hydrandina S.A. for the commissioning of the electricity supply.

In addition, the Control Commission warns that 117 calendar days passed since the presentation of the lifting of observations before the Minedu; However, during this period the National University of Santa has not planned the restart of the electric power work on Campus II, valued at S/ 12 151 127.

The work has an execution balance equivalent to 35.4 % of the physical progress, which demonstrates a lack of forecast by the UNS to guarantee its continuity and culmination, a situation that contravenes what is established in the General Directive of the National Multiannual Programming System and Investment Management of the Ministry of Economy and Finance.

The delay in its culmination harms 2000 beneficiaries, who cannot access laboratories and services. In addition, it affects the functioning of other infrastructure already completed and that are in the stage of equipment, such as projects in the medical unit and academic schools of agronomist and mechanical engineering, whose acts of reception of work date from the years 2021, 2022 and 2023, respectively.

The report was prepared by the Regional Control Management of Ancash and is published in the Control Reporting search engine. It corresponds to the control milestone No. 6, evaluation period from July 7 to 11, 2025, and was communicated to the Rector of the UNS to take corrective and preventive measures to guarantee compliance with the objectives of the project.

Visit us at:

Tiktok: @Contraloriaperu
Flickr: Flickr.com/fotosContraloriaperu/
Instagram: @Contraloriadelperu
Facebook: Comptroller Peru
X: @Contraloriaperu
YouTube: Comptroliatv

Chimbote, July 31, 2025
Corporate Communication Management

Press NOTE N deg 657-2025 CG/GCOC

🔍 Key Information

📄
Tender Reference No.
521135804
📅
Publication Date
01 Aug 2025
🌐
Sector
Education and Training
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 01 Aug 2025
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…