📋 Tender Overview
The Ministry of Mines and Energy (MME) opened, this Friday (23/05), public consultation on the proposal of the 1st Issuance of the Plan of Transmission of Electric Power (POTE) 2025 - Expansion and Reinforcements - Basic Network and other transmission facilities. The participatory process is foreseen in. Interested parties will be able to send contributions for the next 30 days, through.
In the proposal, MME defines the equipment and facilities necessary for the National Interconnected System (SIN), which should be the subject of a grant of the National Electric Energy Agency (ANEEL), including facilities in the transmission systems and also electricity distribution. Indications are made from transmission planning studies developed by the Energy Research Company (EPE) and the Expansion and Reinforcement Plan (PAR/PEL), periodically prepared by the National Operator of the Electric System (ONS).
Through public consultation, society and sector representatives will be able to give their opinion whether indications of expansion and reinforcement are adequate to needs and are compatible with existing facilities. The pote is a fundamental instrument for planning the expansion of the transmission system in Brazil, ensuring that electricity comes safely and reliably, to the entire population. The actions are aligned with the energy planning guidelines, the energy transition and sustainable development of the country.
Main indications of the pote 2025
Among the planning studies, we highlight the reinforcement of the Acre and Rondonia transmission system in response to climate change. These EPE proposals are fundamental to meet Rondonia, integrating the 500/230 kV transmission corridor that connects the AC/RO subsystem to the SIN.
In this edition of POTE, there is also the indication of the interconnection of 230 kV and 525 kV buses of Candiota and Candiota 2 substations in Rio Grande do Sul. This work represents an important evolution for SIN and energy integration between Brazil and Uruguay. The technical solution allows you to optimize infrastructure, eliminating generation flow restrictions, increasing reliability and operative flexibility for energy transfer between countries.
The 1st Issue of POTE 2025 proposes the execution of 36 new expansions in the transmission system, as well as 28 determinations of works for distributors. In this edition, changes and revisions in previous publications are also considered. Complementary documents and information are available on the Ministry of Mines and Energy Public Consultation Platform.
Special Advisory of Social Communication - Mmetelephone: (61) 2032-5759 | E-mail:
* * * *