📋 Tender Overview
During his visit to Tacna, the Minister of Energy and Mines, Luis Enrique Bravo de la Cruz, toured the works being carried out by the Electrosur company in the La Yarada Los Palos district and the Tacna Free Trade Zone.
Together with the president of the board of directors, Hector Liendo Alcazar, and managers of Electrosur, the head of MINEM traveled to the Yarada Electrical Substation, where the execution of the work Creation of the electrical energy distribution service in the new O-166 feeder with a voltage level of 22.9 kv of the Yarada Electrical System begins.
Currently, the project has a physical progress of 54% and upon completion will benefit more than 2,400 families from Los Palos, Santa Rosa and the Santa Rosa Border Complex.
Likewise, he inspected the progress of the execution of the project Creation LT 66Kv Los Heroes - Zofratacna - S.E. Yarada and S.E. Zofratacna, a work that will supply safe and reliable electrical service to 821 industrial lots in Zofratacna and 14 thousand families in the southern area of the Gregorio Albarracin district and the Hospicio sector.
The minister also visited the Control Room at the Para Substation and listened to the presentation of the portfolio of investment projects such as the improvement of the electrical service for various locations in Tarata, Palca and Pachia, as well as the technical file of the improvement of the distribution service in the historic center of Tacna, Moquegua and Ilo through underground networks with an investment of S/108 million.
Bravo undertook to carry out the corresponding steps to achieve the corresponding financing and viability of said investments.