The most advanced projects are found in the regions of Arequipa and Moquegua and add an investment of S/ 717 millionThe Ministry of Energy and Mines (Minem) reported that our country has a portfolio of 14 solar plants that will be built in various regions in the coming years, which will enter into commercial operation until 2028, and will inject 2,447 megawatts (MW) of power to the national interconnected electrical system (SEIN).
These projects are located in the regions of Arequipa, Moquegua and Ica and two of them belong to isolated systems, which will be developed in Loreto; However, all of them will contribute to Peru increasing the renewable energy component of its energy matrix, contributing to Perus energy security and guaranteeing the electricity supply for the entire population.
Of the total portfolio, there are currently 4 photovoltaic generation plants, which are with a greater degree of progress in their construction according to their official reports, and represent a global investment that exceeds US $ 717 million.
Among these projects, we can highlight the Sunny Solar Central, located in the Arequipa region; which will have an installed capacity of 204 MW and an investment that exceeds US $ 177 million.
They are followed by the solar centrals of Solimana and Lupi, both located in the Moquegua region; the first with a capacity of 250 MW and an investment that exceeds US $ 176 million; While the second will inject in the SEIN 150 MW, and its construction will demand an investment greater than US $ 193 million.
The last project on this list is the San Martin Solar Solar Central, also located in the Arequipa region, with a global investment of more than US $ 168 million, and a capacity of 252.4 MW of installed power.
The MINEM highlights that these generation projects with solar technology will contribute to strengthening the countrys energy security, to the creation of employment in various regions, energizing the local economy, and to enhance the resources that Peru has, contributing to the closure of access gaps to the energy of the less favored sectors of the country.
Lima, April 4, 2025