π Tender Overview
The works on the Szeged-Roszke railway line and the new delta track have been completed.The investment not only gives a huge boost to international cargo traffic but also raises everyday travel to a completely new level in the region.
- Faster and more comfortable travel: On the renovated track trains can travel at a speed of 100 km/h and after the issuance of a permit for use up to 120 km/h so the travel time between Szeged and Vojvodina settlements (for example Szabadka) is reduced to 30-40 minutes in addition to the 30-minute mandatory Schengen border inspection time in Roszke.
- Modern stops: the passenger traffic building was completely renovated in Roszke and a new stop was built in Szentmihalytelek.Barrier-free elevated platforms rain shelters and P+R car and B+R bike racks await passengers at both locations.
- Environmentally friendly electric traction: The electrification of the entire line section has been completed so more modern quieter and greener trains can run.
- A more livable environment for the population: More than 1.4 km long noise protection walls were built 7 railway crossings received modern light barriers and nearly 10 km of new excavation roads help local traffic and access to agricultural areas.
- Smoother freight traffic: Thanks to the new delta track international freight trains can pass faster without touching the Szeged-Rendezo station and the frequency of occupancy of the Szegedi ut railway-road crossing is further reduced.
The construction and electrification of the RRF-0.0..2-2026-00016 Szeged-Rendezo - Roszke - Orszahattar railway track - delta track project was realized with the support of the European Union.
MAV Zrt. Communications Directorate