The Geological Service of Lithuania points out that it is mandatory to register all freshwater wells in the subsoil register. In cases where a permit is required for the use of groundwater resources, only enterprises with a permit to explore the subsoil may legitimise such wells.
Validation procedure
1. First of all, it is necessary to submit an application to the municipal administration (the form can be found here) for approval of the use of a well for the extraction of fresh groundwater.
2. With the approval of the municipality, a one-time payment for the legalization of the well must be paid within 30 calendar days.
A one-time payment for the legalization of a well is paid to the account of the STI by selecting the code of that municipality (the codes can be found here), in the territory of which municipality it is planned to legalize the well.
The contribution is not payable if you have paid a fee for the extracted groundwater resources for the last three years before the date of entry into force of the law and during the period of validity of this law, you have submitted an application for approval to the municipal administration for approval of the use of the well.
If a permit is required for the use of groundwater resources, the amount of the contribution depends on the amount of resources:
- up to 10 cu. m meters per day – a one-time payment of 50 euros;
- 10 and more, but up to 100 cu. m meters per day – a one-time payment of 500 euros;
- 100 and more cu. m meters per day – a one-time payment of 5,000 euros.
3. After obtaining approval from the municipal administration for the use of the well, it is necessary to contact an economic entity that has a permit to study the subsoil and conduct groundwater search and reconnaissance. All companies that have permits issued by the Geological Service of Lithuania to study the subsoil can be found in the Environmental Permit Information System ALIS.
4. The holder of the permit shall carry out the steps necessary for the legalization of the well. All actions are specified in the order of the Minister for the Environment on the approval of the description of the procedure for the legalization of wells for the extraction of fresh groundwater not registered in the register of the subsoil.
5. The well must be legalized within 12 months from the date of submission of the application to the municipal administration. Please note: less than a year remains before the end of the temporary law on the legalization of wells for the extraction of fresh groundwater.
6. If the municipal administration has approved the use of the well, it is not possible to record (register) in the Real Estate Register the protection zone of the groundwater watershed, you must liquidate the well within 12 months from the date of submission of the municipal response.
7. In the absence of approval from the municipal administration for the use of the well, it is necessary to apply to an economic entity that has a permit to study the subsoil and conduct groundwater search and reconnaissance. Such a well must be liquidated within 4 months from the date of receipt of the disapproval.
If you have any questions, write to the greziniai@lgt.lt or call +370 670 73333. You can also contact your municipality (municipal contacts here).