Following is a question by the Hon Augustine Wong and a written reply by the Secretary for Development Ms Bernadette Linn in the Legislative Council today February 25
Question
Some members of the construction industry have relayed that in recent years the Government has been launching works projects at varying paces and the timing of tendering for various projects is unevenly distributed resulting in the industry being caught in the predicament of dying from overeating one moment and dying from starvation the next Regarding the tendering arrangements for public works projects of various government departments and projects undertaken by nongovernmental organisations NGOs through entrustment or subvention NGO projects will the Government inform this Council
1 of the following information in respect of the public works projects of various government departments and the NGO projects in each of the past three years i the number of tenders invited ii the number of successful tenders iii the number of unsuccessful tendering iv the total value involved in the award of contracts v the average number of days taken from the closure of tender exercises to the award of contracts and vi the time taken for the five projects which had taken the longest time together with a breakdown by government departments and NGOs
2 whether the Government has plans to further shorten the tendering process such as by enhancing the eTendering System and expediting the assessment of tenders if so of the details if not the reasons for that and
3 given that during the debate on the Members motion on Reviewing the priorities for public works to ensure enhanced speed and efficiency of key projects in this Council on July 16 last year the Secretary for Development indicated that the Government had made a Medium Range Forecast of the capital works expenditure for the next few years which was meant to avoid drastic fluctuations in the volume of public works projects and to provide government departments with an indicator for arranging the priorities of projects whether the Government will in planning public works projects further maintain communication with the industry and where practicable adjust the timing for launching the projects to tie in with the overall resources and capacity of the construction industry thereby avoiding drastic fluctuations in construction volume if so of the details if not the reasons for that
Reply
President
The reply to the three parts of the question raised by the Hon Augustine Wong is as follows
1 The procurement of works projects involves a number of procedures including tender invitation tender evaluation and approval of tender recommendation etc Sufficient time must be allowed to ensure that the entire evaluation process is conducted in a rigorous and comprehensive manner
With regard to tender invitation we are required to comply with the relevant requirements of the Agreement on Government Procurement of the World Trade Organization WTO GPA Where the estimated contract value exceeds the threshold Note stipulated under the WTO GPA the tender invitation period must be no less than 40 days For contracts that are more complex in nature or of higher value the tender invitation period may be extended as needed For contracts with an estimated value below the above threshold although they are not subject to the WTO GPA requirements we generally allow a tender invitation period of no less than three weeks so as to enable bidders to have sufficient time to fully understand various works requirements and assess the associated risks for preparing competitive tenders
As regards tender evaluation we generally adopt the twoenvelope system The evaluation is conducted in two stages we will first assess tenderers technical competence and past performance followed by considering their tender prices During the process clarification may be sought from tenderers in regard to their submissions and legal advice may be obtained where necessary to confirm the validity of the tenders The whole evaluation process typically takes about 25 to three months to complete
For the past three financial years ie 202223 to 202425 statistics on works tenders conducted by government departments and nongovernmental organisations including i the number of tenders invited ii the number of successful bids ie the number of contracts awarded iii the number of tenders not awarded iv the total value of contracts awarded and v the average number of days from tender closing to contract award are presented in the Annex Approximately 80 per cent of the works projects were awarded within five months from the tender closing date
For the five projects that took the longest time from tender closing to contract award the duration ranged from 17 to 23 months Given special circumstances these projects required a longer processing period with the main reasons summarised below
i For one of the projects as the tender prices submitted by the tenderers had exceeded the budget the department concerned had to revise the design of the building foundation and engage all bidders for negotiations The bidders were then invited to adjust their tender prices having regard to the revised design Additional time was hence required to complete the relevant procedures
ii For three football pitch refurbishment projects tenderers were required to propose an artificial turf system in their tenders As the system involved product patents the department concerned had to request supplementary information from the tenderers a number of times and verify through legal advisers whether the proposed manufacturers were the patent holders This led to a longer tender evaluation period as compared with typical works projects and
iii For one of the projects its funding application had to be considered and approved at a later meeting of the Public Works Subcommittee PWSC and the Finance Committee FC of the Legislat