The work will benefit around 146 thousand beneficiaries of Juliaca, ensuring quality water and a new sewage system.In compliance with the commitments assumed by the Ministry of Housing, Construction and Sanitation, the execution of Stage II of the Juliaca Comprehensive Water and Sewerage Program (PIAA) began, a key phase that will improve access to safe water and basic sanitation for nearly 146 thousand families in the city of Juliaca, ensuring greater availability of the service 7 days a week in more than 50 urbanizations.
Stage II of the PIAA Juliaca includes more than 25 thousand household drinking water connections, 4.8 km of pipelines, 2.4 km of primary networks and 94 km of secondary networks. A new drinking water reservoir will also be built and the existing system will be improved. Regarding sewerage, 6,359 connections will be implemented, 6 km of primary collectors, 26 km of secondary collectors and the renovation of 35 km of secondary collectors. The execution period is 540 calendar days.
From the Ministry of Housing we are complying with all the deadlines that we offered to the beneficiaries and we will continue to do so because it is the way to generate trust and demonstrate that this project is a priority in our management, said the Minister of Housing, Wilder Sifuentes Quilcate.
In the first 56 days, the Juliaca consortium, the company in charge of executing this stage and made up of Ingecol Sucursal del Peru and Liydco Engineering S.A.S., will carry out topographical work to identify the streets where the pipes will be installed. In addition, it will carry out detailed social work in order to identify the beneficiaries, framed in the PIAA at Your Door campaign.
In parallel, the company will prepare the Environmental and Social Management Plans (PGAS), and Safety and Health, and will install the camps where the technical and professional personnel will be, as well as the material supply points. The deployment of specialized machinery and the intervention of streets with excavation and masonry work are planned for the end of March.
Data
The PIAA Juliaca megaproject will serve the residents of 217 urbanizations in the districts of Juliaca and San Miguel, who, after more than 40 years of waiting, will have access to drinking water and sanitation services, improving their health and quality of life.