One of the outstanding aspects of the project is the incorporation of technical elements for the proper management of rainwater.Within the framework of the citys reconstruction process, the Provincial Municipality of Piura (MPP) advances in a firm step with the work of improvement of tracks and paths in the human settlement Los Algarrobos IV stage, whose physical execution exceeds 95 %. The project, which represents an investment of S/ 8 461 829.27, is in its final stage.
The Territorial Development and Investment Management reported that this intervention includes items of 227 linear meters of domiciliary water connections, 26 mailboxes, 234 domiciliary drainage connections, 6 757.30 m2 of concrete optimized slab, 9 193.34 m2 of articulated pavement and 4 116.16 m2 of paths, hammers and ramps.
It also contemplates the construction of sardineles, plants installation, 1 379.79 m2 of fat sown, road safety, 14 concrete benches, among other interventions.
The only pending section corresponds to the intersection of L and M streets, where it is necessary to relocate an electrical substation. The Enosa company has already been notified and is doing the corresponding works, so it is expected to complete the paving of this sector in the next few days.
One of the outstanding aspects of the project is the incorporation of technical elements for the proper management of rainwater. In critical areas, 1,760,12 ml of perally sardines and walls up to a meter high to channel the water and avoid entry into homes have been built.
The work includes streets such as J, L, I, K, C and M, with different solutions according to the type of road, whether concrete or cobblestone. Technical specifications are being completed 100 %, including attention to water, drainage and gas connections that generated slight delays, but were properly solved.
FACT
It should be noted that this stage could be executed because the water and sewerage system of the IV stage is in good condition. Stages I, II, III and V have not yet been intervened, since they are part of the network renewal megaproject for 105 human settlements executed by the Ministry of Housing.
The work will culminate in July and will subsequently move on to the reception stage, where a committee will evaluate its functionality and operability.