Construction of hydraulic works advances before the contractual term.The regional governor, Luis Torres Robledo, arrived at Cerro Blanco, in Calana and made an unexpected visit to the construction of R6 and R7 reservoirs, executed by the Regional Government of Tacna, through the Special Tacna project (PET), with an investment S/ 53 million.
It was found that, as of May of this year, the construction of reservoirs 6 and 7 records a accumulated physical advance of 34.5 %, exceeding the scheduled goal. This rhythm of execution has allowed the H2O consortium, responsible for the work, to commit to deliver the project culminated in December 2025, advancing to the contractual term provided for February 2026.
Each of the reservoirs will have a capacity of 385 mm3, which represents a significant improvement in regional water infrastructure. Together, the seven reservoirs projected in Cerro Blanco will add 2 million 695 thousand cubic meters, which is equivalent to approximately one third of the capacity of the Paucarani dam, the main source of water supply in Tacna.
The regional governor personally supervised the work in the area, highlighting the positive impact of these reservoirs on the water security of the population and the strengthening of the agricultural sector.
As part of the environmental commitment, the Executing Consortium will also plant 9,200 native species before the end of the year. Among them are El Molle, Chuve, beautiful grass and Chilco, species that will contribute to reforestation and improve the ecosystem in the sector.