In meeting with the Minem and Congress, Mother of God authorities agreed to end contract with company for delays and reactivate electrification projects in 17 locations.A transcendental work table was carried out in the Ministry of Energy and Mines (Minem), with the participation of the Minister and Deputy Minister of the Sector, the Director General of Rural Electrification, the President of the Congress, and the 11 provincial and district mayors of Madre de Dios.
The meeting had as its central axis the analysis of the state of the four main ongoing electrification projects, as well as the current contract for a new project that will benefit 17 rural locations in the region.
It ends the contract for non -compliance
One of the most relevant agreements in the session was the resolution of the contract with the Inambari consortium, due to the lack of significant advances. The authorities agreed:
Cancel the current contract.
Evaluate the hiring of a new consortium.
Prioritize the elaboration of a new technical file that allows the project to be reactivated.
We need to ensure that each community has access to energy. We cannot allow more delays in fundamental works for rural development, said one of the representatives present.
Next meeting will be key to closing gaps
A technical meeting has been scheduled for April 21, with the end of:
Consolidate the information collected by local governments and the energy sector.
Ensure that all homes are included in the electrification gap closure project.
Strengthen the territorial approach of the ongoing plans.
A joint commitment for a mother of God with energy
The authorities reaffirmed their commitment to work in an articulated and transparent manner, for the benefit of families that still do not have access to the electricity service, recognizing that energy is a basic condition to improve the quality of life and economic development of rural areas.