📋 Tender Overview
Works such as this not only improve transitability, but also strengthen territorial integration, boost the local economy and improve the quality of life of 15 thousand settlersThe Regional Government of San Martin, under the leadership of Governor Walter Grundel Jimenez, continues to advance with a firm step in improving road infrastructure in the region. Through the special Huallaga Central and Bajo May project (PEHCBM), a key stage of the Chazuta - Curiyacu highway improvement project has been successfully completed: the concrete emptying of the upper slab and the eaves of the Curiyacu bridge, a milestone that consolidates the physical progress of this important connectivity work.
Prior to this stage, it was concluded with the installation of the main metal beams that make up the bridge support structure, as well as the formwork and assembly of the reinforcement steel for the upper slab. The Curiyacu bridge, which has an extension of 35 meters of light, has been designed following high engineering standards, which guarantees its operation and resistance throughout the year, even in adverse climatic conditions such as heavy rains in the area.
Currently, the physical advance of the work exceeds 85 % and its culmination is estimated for August of this year, according to the latest PEHCBM report.
With this work, San Martin continues to build roads that unite progress and opportunities for its people. This is possible thanks to the firm political decision of the regional governor, Walter Grundel Jimenez, said Pehcbm manager Javier Sinti Flores.
This work is part of a 19 -kilometer road stretch that joins Chazuta with Curiyacu, directly benefiting more than 15 thousand inhabitants. In addition to the bridge, the project contemplates the construction of sewers, drainage systems, triangular gutters, coronation ditches and other civil engineering solutions aimed at guaranteeing a resilient route against the climatic conditions of the region.