📋 Tender Overview
"Works are actively underway on the remaining two sections of Ricoti. Of course, progress is different. There are also intensive works on the slope near the 149th km, where a potential landslide center was discovered in 2023. Relevant studies were conducted, an engineering solution was prepared, a detour was arranged, a qualified contractor was identified as a result of the tender, who is currently performing a very large-scale work. Mobilization and the pace of works are quite high," said the Minister of Regional Development and Infrastructure, Irakli Karseladze, after getting acquainted with the ongoing works on the first section of Ricoti - Chumateleti-Khevi.
Of the 3 tunnels envisaged by the project on the first - Chumateleti Khevi section of the Ricoti expressway, 2 tunnels have already been cut, 11 bridges have been built out of 17 bridges, and work is underway on 2 bridges. Among them, a 1,800-meter-long tunnel parallel to the historical tunnel of Ricoti has been cut, where the final mowing, drainage and engineering systems are being arranged.
According to the minister, in the framework of the stabilization works of the slope located at the 149th km in the first section of Ricothi, earth masses are being dug, the slope is being developed step by step, after which its strengthening will begin in accordance with the project. After the slope stabilization work is completed, a new road will be built, on which the traffic will be diverted, and the construction of bridges and other infrastructural road elements will begin on the existing road.
"Today's ongoing works are important both from the point of view of slope stabilization and prevention, as well as for the development of the project. In general, there are challenges in the first section of Ricoti, which we are intensively working on with the contractor. Appropriate warnings and recommendations are issued. Irakli Karseladze noted that the pace of work must be increased in the direction of parallel works production.
The Chumateleti-Khevi section is geologically the most challenging section on the Rikot, where one of the main efforts is the stabilization of the slopes with appropriate design and engineering solutions.