📋 Tender Overview
Megaobra will benefit the population of the districts of Eastern Lima, which exceeds 2 million inhabitants.The mayor of Lima, Renzo Reggiardo, today inspected the progress of the new Las Torres bypass, a 1.4 km, six-lane mega-project that the Metropolitan Municipality of Lima has been building, in order to reduce travel times between Lima and Lurigancho-Chosica and speed up traffic on the Ramiro Priale highway.
The work carried out by the Municipal Company to Support Strategic Projects (EMAPE), attached to the Lima commune, includes a third-level viaduct made up of concrete structures and beams up to 40 meters long, which will rise above Las Torres Avenue with the Ramiro Priale highway, which will create a road pair towards the Central Highway.
In statements to the press, the municipal authority announced that this coming January 9, the white march will begin with the opening of a road (Lima-Chosica direction), where two lanes will be enabled from 5 a.m. to 5 p.m. m. to 6 p.m. m., thus benefiting the drivers who will travel through this mega-work.
The work is 95 percent complete. It would be completed in the month of February after finishing the coordination with the Calidda and Sedapal companies, said the mayor, highlighting that the travel time from Lima to Chosica is currently approximately two and a half hours and with the new viaduct it is estimated to be 45 minutes.
The new Las Torres bypass, which will benefit more than 2 million citizens, will have three lanes on each road for the quick and safe circulation of the various vehicular units, achieving better travel times and greater accessibility to areas such as Huachipa, Carapongo, Cajamarquilla, Santa Clara, and others.
Among the components of this important work that began in June of this year, also include the construction of ramps, walls and curbs; In addition, the installation of road safety elements, such as road guards and reflectors, horizontal and vertical signage, LED public lighting and landscaping design.
To date, the concrete structures, such as beams, columns, pillars, slabs and walls, are already ready. In addition, asphalt is being placed on the concrete slabs of the viaduct, and also on the accesses and auxiliary roads.