Electro Oriente will be in charge of executing both the temporary measures and the definitive solution to ensure the reliability of the supply.With the objective of providing reliability to the energy supply chain, the Ministry of Energy and Mines (MINEM) declared a situation of serious deficiency in the electrical service in the Tarapoto and Yurimaguas Electrical Systems, through Ministerial Resolution No. 408-2025-MINEM/DM, issued on December 1, 2025.
The declaration of serious deficiency in these locations is established by the lack of transmission capacity in the 138 kV Tingo Maria - Aucayacu - Tocache corridor, a situation that puts the continuity of the electricity supply in both locations at risk.
The decision is based on Supreme Decree No. 044-2014-EM, which authorizes the MINEM to declare situations of serious deficiency to ensure the reliability of the energy supply in the National Interconnected Electrical System (SEIN) and the Isolated Systems.
As part of the temporary and immediate measures established, the standard establishes that the additional electricity generation capacity, necessary to ensure timely supply, consists of the installation of 6.2 MW of emergency generation in SE Tarapoto by the company Electro Oriente.
Likewise, it was designated as the company responsible for executing both the temporary measures and the alternative permanent solution.
The resolution provides that, within the first three months of issuance, the electricity distributor must send the MINEM the schedule and the file of the contracting of works, services or goods. Additionally, it must report, on a semiannual basis, the progress of implementation and the measures adopted, under the guidance of the General Directorate of Electricity.
The validity of this declaration will remain until the commissioning of the ITC Link 220 kV Belaunde Terry - Tarapoto Norte (2 circuits), extensions and associated substations project, scheduled for February 29, 2028 at the latest.
The MINEM reaffirms its commitment to strengthening the national electrical infrastructure, guaranteeing the countrys energy security and promoting conditions that promote the well-being of families and the economic growth of the region.
Lima, December 6, 2025