📋 Tender Overview
Five bidding companies carried out a field visit to the intervention areas, as part of the process prior to the award of this important work.The Ministry of Housing, Construction and Sanitation continues to comply with the schedule established for the execution of the Juliaca Comprehensive Water and Sewerage Project (PIAA). Within the framework of Stage 4, five companies interested in developing the work participated in a field visit to the areas where the intervention will be carried out.
This activity was carried out after the publication of the call for bids, on January 25, and the information meeting held on February 4, thus consolidating the milestones planned for this phase of the project.
During the tour, the bidders were able to recognize the land where 9 reservoirs, 7 primary and secondary networks, 16 pumping stations will be built, as well as conduction and adduction lines, home sewage connections and other complementary works that will allow the expansion and improvement of basic services in the city.
According to the schedule, the presentation and opening of proposals will take place on March 21; The notification of the award is scheduled for June 17, and the signing of the contract is scheduled for July 22. Stage 4 of the PIAA Juliaca contemplates an investment of S/833.1 million.
The progress of the project was reported in a meeting with the leaders of the PIAA Juliaca Central Committee, which included the participation of the MVCS technical team, as well as local authorities and representatives of the sector, including the provincial mayor of San Roman, Oscar Caceres; the district mayor of San Miguel, Cristin Mamani, and the manager of SEDAL Juliaca, Fredy Carita, as well as beneficiary residents.
In this space, the status of the four stages of the megaproject was also detailed: the first already completed; the second in the topographic survey and socialization phase; the third in the contract signing process, scheduled for February 20; and the fourth currently in tender.
Data
The PIAA Juliaca, in its four stages, will benefit more than 370 thousand residents of 217 urbanizations in the districts of Juliaca and San Miguel, who, after more than 40 years of waiting, will access drinking water and sanitation services, improving their health and quality of life.
General Communications Office