📋 Tender Overview
It was paralyzed due to lack of resources by expiring reconstruction with changes. Work balance file provides for the integral improvement of the asphalt folder in the intervened roads and not only stop the AreExcellent news for the inhabitants of the eight urbanizations harmed by the stoppage of a sanitation work in Trujillo. Mayor Mario Reyna said that after the settlement of the contract of the work was approved, that the executing consortium gave its compliance, and that the work balance file was approved, the MPT will finish it.
This is the rehabilitation of networks and domiciliary connections of sewerage in the urbanizations San Andres, Vista Hermosa, Trupal, El Rob, San Nicolas, Vista Bella, Huerta Grande, Santa Teresa de Avila; and the streets Manco Capac and Jose de la Riva Aguero, of the El Porvenir District.
The work was paralyzed due to lack of financing when reconstruction with changes, and problems with the contractor, the Trujillo Crece consortium, which abandoned the execution because the contractual period of work execution and could not comply with the established deadlines, so they would receive penalties were noted.
Reyna explained that the MPT will culminate the work and that next week the call will enter to tender the execution of the balance. The most important thing is that the new file not only includes the replacement of the intervened area but will improve the asphalt surface of the intervened roads, he said.
With resolution of the Public Works Management No. 076-2025-MPT/GOP, the technical file of the work balance was approved-which includes the intervention in the improvement of the sanitary sewer system-, disassembly and elimination of existing pipes and mailboxes, elimination of clearing, stroke and rethinking, leveling, rehabilitation of the existing sanitary sewer network and replacement of asphalt.
With Public Works Management Resolution No. 083-2025-MPT/GOP, the ex officio settlement of the work contract was approved, for an executed advance of 80.08%, as well as the one not executed (19.92%), in accordance with the technical expertise validated in the execution.
The important thing is that the Trujillo Consortium grows (composed of EIRL imports and services and large SAC XTRUCTURES), represented by Juan Razuri Ruiz, gave its compliance to the work settlement resolution, requesting the pending payments and the return of its guarantee guarantee fund is complied with
The work began in 2023, in the management of Arturo Fernandez, with an amount of S/ 10,294,095.16 and execution period of 150 calendar days; and thousands of families were harmed by their paralysis, so Mario Reyna promised to complete it.
To minimize the inconvenience in the population, the ditches that were open were temporarily covered, to solve the problem. There were several attempts to liquidate the work, which was paralyzed for more than a year, and the MPT, after technical studies and expert studies, culminated the work balance file so that its execution was convened to tender.
This year we separated budget to continue the work. That was the commitment to the affected population. Today we are fulfilling the word committed, when the continuation resumes, said the burgomaster, emphasizing that not only the work areas will be stopped but that the entire folder will be renewed in the intervened streets.