Hundreds of farmers and residents of the La Yarada Los Palos district will soon enjoy a more optimal and reliable electrical service with the work Creation of the electrical energy distribution service in the new O-166 feeder with a voltage level of 22.9 kv of the Yarada electrical system, which is being executed by the company Electrosur, presenting a current physical progress of 54%.
With an investment of more than S/4.2 million, the execution of the work began on September 18, 2024 and to date work is being carried out to transport materials, transport poles to the lifting point, dig holes and lift 118 poles 15 meters high, reported Wilder Aguilar Cancina, construction resident of the Zeki Consortium.
The purpose of the project is to improve product quality, increase supply and correct deficiencies in the O-166 feeder, with the installation of 15 km of medium voltage line, benefiting the sectors of Santa Rosa, the border complex and Los Palos.
The physical execution period is 150 calendar days. To date, the work is progressing according to the schedule and its completion in February 2026 is assured within the scheduled time, said supervisor Victor Ticona Palle, indicating that, upon completion, the project will guarantee a supply of 6 MW per year for the next two decades.
By repowering the electrical service, farmers in the border district will be able to increase the production and processing of olives, oranges, onions, watermelons and other products, giving added value to their agro-industrial activities.
We, the residents of La Yarada Los Palos, need electricity service, both for agriculture and in the homes for our children who are studying. It is very important to have energy, commented a farmer from the district.
In this way, Electrosur is committed to improving the quality of life, the economy and the development of the living borders and the Tacna region.