The Directorate of Roads and Highways (RSD) has started building the 2.3 kilometer long Lvova bypass on the I/13 road in the section between Novy Bor and Liberec. The price of the construction which resulted from the tender process is almost 630 million crowns without VAT. It will be used from June 2028. The goal is safer and smoother traffic on one of the key roads in the region the bypass will divert transit traffic from Lvova.
Follow @min_dopravy
View gallery (1) Although the connecting sections of the I/13 road have already been modified in the past in Lvova the road still runs through a built-up part of the village. The new interchange will divert transit traffic from the village and it will be safer for the locals to move along Lvova. In addition the length of the interchange is shorter than the current route which will speed up the journey for everyone. We are now building almost 70 kilometers of Class I roads in the Czech Republic mostly bypasses which improve the living conditions of the locals and they make roads easier for motorists says Transport Minister Ivan Bednarik.
According to the latest traffic census from last year 12600 cars of which almost 1500 are heavy trucks drive along I/13 through Lviv every day. The interchange will be three-lane with two lanes leading towards Liberec. The construction will include four bridges an overpass and six retaining walls. The longest of them will measure over 200 meters and be almost 17 meters high. There will also be four anti-noise walls almost a kilometer long.
This is a section that follows on from the two already operational bypasses which are the Jablonne bypass in Podjestedi and the bypass of road I/13 in front of the village of Rynoltice. When preparing the Lvove bypass we emphasized minimizing the impact of the construction on valuable natural sites around the Panenske brook in order to protect the residential development of the village of Lvova as much as possible and to respect the protected area of the Luzicke hory PLA. Road The I/13 forms the backbone of the transport system in the entire area connecting the Usti and Liberec Regions said Radek Matl CEO of RSD.
The RSD is preparing a number of other projects on the I/13 road. At the beginning of the 1930s for example the Kladrubska Spojka should be completed in the Usti Region and in the Liberec Region among other things an 8.5-kilometer switch between Krasna Studanka and Detrichov.
I/13 Rynoltice-Lvova transfer
Main route:
length: 2360 m
number of all buildings: 60
anti-noise walls: 4 total length 988 m
contractor: association MI Roads a.s. BES s.r.o. and Metrostav DS a.s.
construction price according to the contract: 624483447 CZK without VAT
start of implementation: 3/2026
commissioning: 6/2028
length of construction until commissioning: 27 months
The Directorate of Roads and Highways will have a total of 226.7 kilometers of new buildings under construction by the end of the year. These are 157.4 km of highways and 69.3 km of Class I roads.
Another 116.7 km of highways and Class I roads are in the tender process.