📋 Tender Overview
o Measure will ensure the timely supply of electrical energy while the 138 kV San Rafael - Ananea Derivation Link project is being executed.Within the framework of its commitment to guarantee the continuity, security and reliability of the electricity supply throughout the country, the Ministry of Energy and Mines (MINEM) declared the electrical service at the Ananea Substation, in the Puno region, in a situation of serious deficiency, due to the lack of transmission capacity.
The measure was made official by Ministerial Resolution and will be valid from February 24, 2026 until the commissioning of the project 138 kV San Rafael - Ananea Derivation Link, extensions and associated substations (ITC Project), scheduled until November 2029 at most.
The MINEM explained that the declaration of serious deficiency, after the technical analyzes carried out by the General Directorate of Electricity (DGE), responds to the need to ensure the timely supply of electricity supply in the Puno region, while the definitive infrastructure is completed that will allow the transmission system to be reinforced and meet the growth in demand.
In this sense, the governing body established that the additional temporary electricity generation capacity necessary to cover the demand associated with the Ananea Substation will be up to 10 megawatts (MW) during the year 2026, up to 11 MW in the years 2027 and 2028 and, finally, up to 12 MW in the year 2029.
Likewise, the company Electro Puno S.A. was designated so that, in compliance with Supreme Decree No. 044-2014-EM, it implements the necessary measures to overcome the situation of serious deficiency declared.
As part of the adopted provisions, Electro Puno S.A. must send to the MINEM, within the first three months of issuing the Ministerial Resolution, the schedule and file of the contracting of works, services or goods linked to the implementation of the measures; and report semiannually on the progress of the execution of said actions, under the supervision of the DGE.
With this decision, the MINEM reaffirms its commitment to strengthening the national electrical system, prioritizing timely solutions that guarantee a safe and reliable supply for the population of the Puno region, while executing structural investments that will consolidate the energy development of the south of the country.
Lima, February 25, 2026