📋 Tender Overview
A ceremonial handover of the construction site of the future judicial complex took place today in ?eské Bud?jovice with the participation of the Minister of Justice Pavel Blažek, Deputy Minister of Justice Radomír Da?hel, Governor of the South Bohemian Region Martin Kuba, Mayor Dagmar Škodová Parmová, representatives of the courts, the Public Prosecutor's Office and the contractor."I would like to thank the Mayor, the Governor, the representatives of the courts, in short, everyone involved in the project of the new judicial complex. I believe that the final effect of the reconstruction of the buildings of the former Žižka Barracks will be the overall simplification of the organization of the South Bohemian courts and ensuring the proper functioning of the District Court in ?eské Bud?jovice, the Regional Court in ?eské Bud?jovice, the District Public Prosecutor's Office in ?eské Bud?jovice and the District Court in Tábor," said the Minister of Justice during the ceremonial launch of the construction.
"The activities of the court at multiple workplaces are not only organizationally demanding, but also financially demanding and cause complications for both the parties to the proceedings and the public. By building the judicial complex, we will achieve the concentration of judicial units, increase efficiency and, last but not least, economic savings," added Deputy Minister of Justice Radomír Da?hel.
The Minister of Justice discussed the implementation of the joint project of the Ministry, the City and the Region, the preparation of which began in 2012 under Minister Pavel Blažek, with Mayor Dagmar Škodová Parmová and Governor of the South Bohemian Region Martin Kuba during his business trip to ?eské Bud?jovice. By reconstructing two existing buildings and completing one new building, it will be possible to use the current premises for the new seat of the District Court in ?eské Bud?jovice, whose existing premises are already unsuitable and cramped, and for the District Public Prosecutor's Office.
This is currently one of the most important investment projects of the Ministry of Justice of the Czech Republic, which took over the management of the site in March 2023 and completed the tender procedure for concluding a contract for work with the contractor in March 2024.
The subject of the work is:
1. Complete reconstruction of the existing buildings of the former Žižka Barracks, including the completion of the new central building of the future judicial complex of the District Court in ?eské Bud?jovice and the District Public Prosecutor's Office in ?eské Bud?jovice, including the related transport and technical infrastructure for almost CZK 600 million.
New premises:
2. It is planned to build a total of approx. 2200 m2 of office space for 190 employees, 19 courtrooms, almost 1000 m2 of registries and the construction of other operational premises with a total usable area of approx. 7300 m2.
3. The construction of a new complex consisting of two reconstructed buildings A and B and a new multi-purpose building C for the above-mentioned organizational units of the state will not only increase the usable area for individual judicial organizations so that they meet the current and future necessary capacities, but also the safety requirements of the operation and security of judicial buildings.
4. Increased demands are also placed on the energy performance of new premises. The use of renewable energy sources and a reduction in operating costs are expected.
5. Last but not least, the joint location of the District Court and the District Public Prosecutor's Office will lead to a more effective operation of their activities and the method of protection and guarding, including a reduction in the necessary number of judicial guard posts.