📄 Tender ID: 519386783 📅 Published: 20 Jun 2025

📋 Tender Overview

The placement of the hot asphalt continues on the runway and the geodrens installation is already being planned to mitigate the humidity on the trackWhile the Peruvian Corporation of Airports and Commercial Aviation (CORPAC) continues with the maintenance works at the Francisco Carle de Jauja airport, the Sky Airline Peru airline confirmed the resumption of its flights to said destination from next Tuesday, July 1, together with Latam Airlines, which will also do so since that day.

Today the placement of hot asphalt continued on the runway despite the rains that have been falling in recent days and reduced work hours in the air terminal.

Likewise, the GeodReen design and planning have been working for installation that will allow the problem of moisture and filtration detected in the airstrips of the landing floor. This filtration, which increases in the rainy season, generates a hydraulic pressure that puts the structure of the pavement at risk, compromising the base and subbase, being able to cause deterioration such as fissures, pumping or settlements of the asphalt folder.

🔍 Key Information

📄
Tender Reference No.
519386783
📅
Publication Date
20 Jun 2025
🌐
Sector
Aviation
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 20 Jun 2025
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…