The reconstruction of the oldest highway bridge in the republic the Smejkalka bridge on 24 km of the D1 highway entered the next phase. Half of the supporting structure in the direction of Prague was demolished. Now it is being rebuilt. Traffic on the freeway remains two lanes in each direction.
Follow @min_dopravy
View gallery (2) After the demolition of half of the supporting structure separation and transport of rubble the reconstruction of half of the bridge in the direction of Prague was started. Intensive concreting is underway on site. In total approximately 7000 cubic meters of concrete will be used for the reconstruction of the bridge.
We want to have the first half of the bridge reconstructed by the end of the summer holidays. This will be followed by the demolition and reconstruction of half of the bridge in the direction of Brno. Later the historical arch will also be renovated which will remain from the original bridge. Dozens of workers take part in the construction every day. They have a lot of heavy equipment at their disposal including crawler excavators truck cranes or tower cranes with a height of 60 meters.
Traffic on the highway is still conducted in the 2/2 mode with narrowed lanes at the site of the work. The speed at the construction site is reduced to a maximum of 80 km/h and compliance with it is controlled by stationary radars. The local road under the bridge connecting Senohraby with Hrusice remains closed.
The contractor is the association of companies Strabag a.s. and Pragoprojekt a.s. which is reconstructing the bridge for 965 million CZK excluding VAT. The work is progressing according to the schedule which still envisages putting the reconstructed bridge into operation in July 2027.