📋 Tender Overview
- Research center for the Tulumayo headquarters is being executed without hydraulic design, water availability or feasibility of electrical energyHuanuco.- The Comptroller General of the Republic (CGR) warned that the National Agrarian University of La Selva is carrying out a research project for the Faculty of Animal Science with an incomplete technical file. This document lacks hydraulic design, feasibility of electrical energy and water availability, which could lead to work stoppage and delay the objectives of public investment.
Concurrent Control Report No. 17480-2025-CG/GRHC-SCC (evaluated from October 20 to 22, 2025) reveals that the project file for Improvement of the science, technology and innovation promotion service for the Tulumayo headquarters does not have the hydraulic designs of the projected sanitary system.
During the inspection of the first stage of the project, it was verified that there is no design that supports the projected dimensions of the tubular well, nor geophysical and hydrogeological studies. This implies the risk of carrying out 80 meters of excavation without reaching an aquifer, which would make the underground water supply unfeasible due to the absence of technical studies.
The hydraulic designs not considered correspond to the components of the percolator well, septic tank, biodigesters, tubular well, cistern, elevated tank, riverside defense, drainage system and external water and drainage networks. These technical deficiencies could lead to the stoppage of the work, as well as the approval of additional or deadline extensions.
Likewise, the projected tubular wells do not have the availability or authorization for water use issued by the National Water Authority (ANA), which represents a risk for the continuity of the project.
Furthermore, the technical file approved for the Tulumayo headquarters does not have the feasibility of supplying three-phase electrical energy, despite the fact that the project contemplates the acquisition of equipment that requires this type of energy, such as processing plants, laboratories, warehouses, a generating set, a pump room, among others.
In the town center of Santa Lucia, where the headquarters is located, there is only one single-phase line; The nearest three-phase power is seven kilometers away. Regarding the substation considered in the file, if this deficiency is not corrected, there is a risk that the equipment will become inoperative at the time of its commissioning.
The technical file with which the Tulumayo headquarters began in January 2025 had deficiencies. Despite this, it was approved in August 2024 and used to contract the execution of the first phase for S/ 13.3 million. However, UNAS has projected, with this same file, the execution of other similar research centers at the Zungaro, Acuayacu and Tingo Maria headquarters, which will be developed in stages with a total budget of S/ 83.2 million.
The Comptrollers Office recommended the head of the entity to adopt corrective actions in order to ensure compliance with the objectives of public investment. The report is published in the Control Services Report Search
Visit us at:
Twitter: @ContraloriaPeru
Flickr: flickr.com/fotoscontraloriaperu/
Facebook: Comptroller Peru
Instagram: @contraloriadelperu
YouTube: ContraloriaTV
TikTok: @contraloriaperu
Huanuco, November 25, 2025
Communications Management
PRESS RELEASE Ndeg 984-2025-CG/GCOM