- Comptrollers Office warns of non-compliance in works carried out by the Puyango Tumbes Binational Special Project Projects for the rehabilitation and expansion of water service for irrigation are carried out with lTumbes.- The Comptroller Generals Office detected that the rehabilitation work of the water service for irrigation of the La Pena canal, in the districts of Corrales, la Cruz and San Jacinto, with an investment of S/ 25 million and in charge of the Puyango Tumbes Binational Special Project (PEBPT), was received and settled without applying penalties for non-compliance in the execution, which affects the use of resources and compromises the safety and sustainability of the service.

In the Concurrent Control Report No. 003-2026-OCI/3414-SCC (evaluation from January 28 to February 3, 2026) it was revealed that an essential item linked to the detailed engineering of the electromechanical system was not complied with, which had technical observations and failures in the lifting system (lifting heavy loads), and that the Comptrollers Office reported to the PEBPT. In this regard, the control commission confirmed the fracture of a gear and the fall of a gate.

However, the entity did not order the application of the maximum penalty to the contractor for non-compliance with the item, nor to the supervisor for granting technical conformity without support, allowing the reception and settlement of work to be carried out.

In the project to expand the water service for irrigation in the La Tuna sector, for S/ 23 million, technical deficiencies were evident that affect the quality of the work, such as segregation of concrete (separation of its components: stone, sand, etc.), cracks in one of the canal panels, which could be associated with deficiencies in its construction or quality of the material used, and presence of rust in the steel rods of the pump house, which would compromise the durability and resistance of the structural elements.

The events were alerted to the entity in a control milestone report from December 2025, which shows the continuity of the risk and inaction of the PEBPT. In addition, auditors from the OCI PEBPT were present during the pouring of concrete in the canal panels, which is why they required test tube tests to verify its quality; However, the staff did not have the equipment, demonstrating the insufficient implementation of control mechanisms.

Also, in the Control Milestone Report No. 002-2026-OCI/3414-SCC (evaluation from January 23 to 29, 2026), the absence of the supervisor and his staff during the execution of the work is noted, where only one specialist was found, a repetitive situation, which was also warned and communicated in a previous control report. This generates the risk that the work is carried out with technical deficiencies that affect its quality and useful life.

The reports are published on the institutional portal www.gob.pe/contraloria for the sake of transparency and access to information.

Tumbes, February 17, 2026
Communications Management

PRESS RELEASE Ndeg 162 - 2026-CG/GCOM

🔍 Key Information

📄
Tender Reference No.
529042011
📅
Publication Date
18 Feb 2026
🌐
Sector
Water and Sanitation
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 18 Feb 2026
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…