- Main channel has several cracks and water seepage is observed in the valvesHuancavelica.- The Comptroller General of the Republic (CGR) warned that officials from the District Municipality of Anchonga received, in November 2025, a technical irrigation work, despite the fact that it presented cracks and technical deficiencies that put the durability and quality of the hydraulic structure at risk. The project valued at nearly S/ 6 million will benefit 864 farmers in the area.
According to Concurrent Control Report No. 001-2026-OCI/0394-SCC, on November 24, 2025, the work reception committee, together with the supervisor and the work resident, carried out the project inspection and concluded that the observations identified a week ago had been raised, for which they proceeded to sign the Work Reception Record.
However, when the audit commission carried out the inspection of the work on December 11, 2025, it was noted that the irrigation canal has cracks in the side walls of the concrete structure of the main canal, in the located sectors, from the progressive 0 + 000 m to 0 + 325 m, a situation that could cause water seepage into the ground, affecting the useful life of the work that has been built to optimize the use of water and agricultural resources.
Likewise, they found technical deficiencies in the installation of gate valves of the water distribution network, whose concrete boxes have water inside (sides 6 and 14), which would indicate that the valves show a leak or filtration due to the poor installation of their accessories. It should be noted that these valves are designed to allow or completely interrupt the passage of water (open/closed) using a wedge or vertical disc.
The audit commission also observed that the entity has not updated the information on the progress of the work in the Public Works Information System (Infobras), a situation that limits access to information on the execution of public works, as well as the exercise of social control by the competent bodies and citizens. Although the work had already been completed, the entity recorded a physical progress of the work of 26.8% as of May 2025; That is, the information had not been updated.
The Comptroller Generals Office notified the head of the District Municipality of Anchonga of the adverse situations identified so that he could implement preventive and corrective measures in the next five business days, which must be supported before the Institutional Control Body of the Provincial Municipality of Angaraes that carried out the control service.
DATA:
The next concurrent control report will be carried out on the settlement process of the work contract Improvement of the water provision service for irrigation in the technical risk system of the town of Anchonga, district of Anchonga, province of Angaraes, department of Huancavelica.