- They warn of failures in the quality of the pavement and risks of improper payments in the work of the El Tambo districtJunin.- The Comptroller General of the Republic (CGR) detected deficiencies in the execution of the balance of work of the project Improvement of the local road system of the Justicia Paz y Vida human settlement of the district of El Tambo - Huancayo - Junin, work valued at more than S/ 21 million, carried out by the Ministry of Housing, Construction and Sanitation, which seeks to improve the walkability and quality of life of the residents of the sector.
According to the Control Milestone Report No. 096-2025-OCI/5303-SCC, construction deficiencies were identified such as cracks in the asphalt layer, speed bumps and road intersections in poor condition, and deterioration of the sealing material (elastomeric seal) that serves to join the tracks and provide adequate operation in the face of expansion and contraction due to temperature. These failures can cause water infiltration, loss of support, potholes and a reduction in the useful life of the pavement, in addition to evidencing non-compliance with technical specifications and the National Building Regulations.
The report also warns that the asphalt and road marking works were valued (economic value of the construction) at 100%, despite not being completed at the time of the inspection. This situation contravenes the provisions of the technical specifications and the Regulations of the State Contracting Law, generating the risk of improper payments and non-compliance with the quality factors provided for the work.
The project contemplates the rehabilitation and improvement of the internal roads of the Justicia Paz y Vida human settlement, including the paving of streets and sidewalks, the construction of curbs, gutters and sewers for adequate storm drainage, as well as the implementation of road signs and accessibility ramps for pedestrians and people with reduced mobility.
The Comptrollers Office recommended that the responsible entity urgently adopt preventive and corrective actions that guarantee the quality and effective completion of the project. Likewise, it will continue to carry out concurrent control actions to verify that the execution of the work complies with technical and contractual standards, ensuring that public resources are used efficiently and for the benefit of citizens.
DATA:
- Although the execution of the balance of work should have been completed in May 2025, the progress made as of September of this year only reached 93.8%, which reflects delays in the completion of the planned work.
Visit us at:
Twitter: @ContraloriaPeru
Flickr: flickr.com/fotoscontraloriaperu/
Facebook: Comptroller Peru
Instagram: @contraloriadelperu
YouTube: ContraloriaTV
TikTok: @contraloriaperu
Huancayo, October 30, 2025
Communications Management
PRESS RELEASE Ndeg 917-2025-CG/GCOM