- Project began in 2021 with S/ 97 million, however currently costs more than S/ 456 millionAncash.- The Comptroller Generals Office warned that the work to improve the II-I Support Hospital in the province of Recuay remains paralyzed due to the increase in its budget and the lack of resources.

The work, carried out by the National Infrastructure Authority (ANIN), began in May 2021 with an investment of S/ 97,397,247, however, to date it remains suspended with an updated investment cost equivalent to S/456,995,886.

According to Official Guidance Report No. 12191-2025-CG/MPROY-SOO, (evaluation period from September 22 to 25), the works were initially scheduled to be executed in 533 days, however, 1,585 days have elapsed and there is 78.56% physical progress. Added to this is that the initial investment amount of the project has increased by 370% due to compensable events, deadline extensions, design modifications, among other causes.

At the beginning of August, the project management, representing the ANIN, decided to suspend the work for eleven weeks due to the lack of resources to continue making payments. Decision that, it is warned, will generate an impact on the deadline and costs of the work, and will affect the beginning of the provision of health services to the population.

All of this would make it difficult for the National Infrastructure Authority to carry out a correct multi-year programming of the budget requested for the execution of the project. That is, there is an uncertain outlook regarding the total cost and the actual completion date; Therefore, it is up to ANIN to make an honest assessment of the projection of the final cost of the project.

It is worth mentioning that in July of this year the contractor issued an early warning notification in which it warned that due to the lack of payment of the valuation for the month of June, the work could be paralyzed again. Along these lines, at the end of that same month the project manager reported the lack of resources to comply with the payments, given that the Ministry of Economy and Finance did not approve an additional budget for the ANIN.

The report was communicated to the head of the National Infrastructure Authority with the aim of adopting the necessary actions to ensure the continuity and completion of the work, for the benefit of the population that uses health services. Likewise, citizens can access the full content of the document through the Control Report Search.

FACT:
The construction project of the new Health establishment in Recuay has category II-1 and includes the construction of a main hospital infrastructure of five (5) levels, temporary environments for patient care (Contingency Plan), equipment, studies, among other aspects.

Visit us at:
TikTok: @contraloriaperu
Flickr: flickr.com/fotoscontraloriaperu/
Instagram: @contraloriadelperu
Facebook:ComptrollerPeru
Twitter: @ContraloriaPeru
YouTube: ContraloriaTV

Ancash, October 14, 2025
Communications Management

PRESS RELEASE Ndeg 864-2025-CG/GCOM

🔍 Key Information

📄
Tender Reference No.
523931923
📅
Publication Date
16 Oct 2025
🌐
Sector
Infrastructure and construction
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 22 Oct 2025
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…